Ryebridge Construction was awarded the contract to deliver the Port of Harwich Entrance works, secured by competitive tender. Ryebridge has over ten years’ experience working in restrictive operationally constrained environments such as Airports and this experience was invaluable in successfully delivering the project.
The fundamental objective was to ensure that the works were successfully completed with no ongoing operational impact for the client. The existing freight entrance was adjacent to the new entrance and it was business critical that the main entrance and surrounding areas were kept operational.
Installation of service ducting
Demolition of existing control facility
Construction of insitu RC foundation and base slab for new facility
Re-configuration of existing Port entrance involving kerbing, drainage, asphalt surfacing, road marking and security fencing
Installation of new control facility canopy building
Relocation of all IT and electrical control systems