Project Works and Key Quantities
Excavation
18500m3 Material recycled and re-used within the works
4500m3 Supply and compaction of Type 1
12500m3 Cement Bound Granular Material
15,700T Foam Base
4800T Asphalt Surfacing
19500m2 Asphalt reinforcement grid
14200m2 PQ Concrete
2200m3 Drainage
4000m Attenuation Tanks
1750m3 AGL Pit and Ducting System
7000m and 104 Pits Complete on time and under budget
Complete on time and under budget
Project Principals and Objectives
The project was to construct a new taxiway in order to enable growth in passenger numbers and flights using the airport. In addition, to extend an existing aircraft stand at either end to accommodate 2 additional aircraft. The third area of works was to reconfigure an existing executive aircraft stands to accommodate additional aircraft and new roadway for aircraft maintenance vehicles and plant.
For more information click on the image below.