Project Works and Key Quantities
Demolition of 4No Hangars and Buildings including asbestos removal – 9000m2 total
Establishment of airside/landside compliant fencing
Waste management and disposal of contaminated ground – H62 demise
Site clearance and formation preparation
Excavation and disposal – 6500m3
Diversion of key services including HV main and installation of new sub-station
New drainage including interceptors – 5km
Installation of acoustic fencing inclusive of foundations – 125m 4m high
Installation of high mast lighting – 8No
Recycling and crushing to re-use broken out pavements including certification – 3000m3 (passed on to Client as a saving)
New aircraft pavements – 14000m2 PQ
Concrete – 6000m3
Supply, lay and compaction Type 1 – 5400m3
New AGL installation including new pit and duct network
Foundations and substructure for new FBO – 3200m2
Block paving – 2800m2
Asphalt – 4200m2
Kerbing – 2500m
Project Principals and Objectives
The project was the demolition of 4No existing Hangars over several phases, construction of a new aircraft apron and cargo compound, groundworks and external works to the new FBO for Signature Flight Services at their existing location at London Luton Airport.
The key objective was to minimize disruption to their existing flight services and London Luton Airport.